20130612 - Meeting minutes, Wednesday , June 12th, 2013
OpenNCP Weekly Sprint Meeting
11th Jun 15:00 to 16:00 CET
- reschedule for > 12th Jun 10:30 to 11:00 CET
Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?) Completed
- Release date: 25March (Monday) > OpenNCP 2.0.0 > Postpone
5º Sprint: 25Mar > 8Apr (2 weeks) Completed
- Release date: 10Apr (Thursday) > OpenNCP 1.1.2 > Completed (Release Notes)
- Release date: 11Apr (Thursday) > OpenNCP 2.0.0 > Postpone
6º Sprint: 22Apr> 3May (2 weeks) > Completed
- Release date: 8May (Wednesday) > OpenNCP 1.1.3 > Completed (Release Notes)
7º Sprint: 6May> 17May (2 weeks) > Completed
- Release date: 22 May (Thursday) > OpenNCP 2.0.0 (Postpone)
8º Sprint: 20May> 31May (2 weeks) > Completed
- Goal: PAC + HCER QA
9º Sprint: 3June> 14June (2 weeks) > in Progress
- Support OpenNCP 1.1.3 (used in )
- Release OpenNCP 2.0.0 > 19 June (Thursday)
Agenda
1. PAC QA Stage
2. HCER QA Stage
3. epSOS 2.0 Audit Trail EventIDs (Discussion of Roadmap)
4. 4PPT OpenNCP usage feedback
5. OpenNCP Support
6. epSOS2: TSAM adaptation for CTS2 compliance
Location
NetViewer + VOIP (Netviewe session number: 369 152 647)
Participants:
1. PAC QA Stage
2. HCER QA Stage
3. epSOS 2.0 Audit Trail EventIDs (Discussion of Roadmap)
4. 4PPT OpenNCP usage feedback
- No issues were raised.
- General feedback is really positive, having in mind that all the participating PN accomplished the PPT goal.
- Regarding OpenNCP no difficulties have been reported....
- Some feedback from Mustafa about the 4th PPT
From Mustafa email:
Kostas Karkaletsis: As expected, results are perfect. There is only one minor issue: eD audit test of Croatia is missing, more information provided in the report.
- Do all PN participating in the 4PPT used the OpenNCP?
- Probably YES;
- Who were the PN participating? Malta, Slovenia, Croatia; Hungary;
- The OpenNCP has provided an 1.1.4 branch, for Hot Fixes that may arise for the 4th PPT.
- The branch was not used, so it may be closed, and there is no need to merge it with the OpenNCP 2.0.0.
- The branch was not used, so it may be closed, and there is no need to merge it with the OpenNCP 2.0.0.
1. Mika has fixed the database connection leaks, changes are in develop branch. (INT-62 and TSAM-1)
- PT: Had some evidences of this problem in our training environment;
- PT needs to restart the Application Server (Apache) very often regarding some leaks;
2. During the merge of 1.1.3 and develop branches some functionality was lost, check INT-63.
BLOCKING ISSUES TO SOLVE
- ++++++++++++++++++++++
From: Marcelo Fonseca <marcelo.fonseca@iuz.pt>
Subject: Clarification on new Audit Messages specifications
Date: 12 June, 2013 12:35:23 PM GMT+01:00
To: Jörg Caumanns <joerg.caumanns@fokus.fraunhofer.de>, Sören Bittins <soeren.bittins@fokus.fraunhofer.de>
Cc: Marcello Melgara <marcello.melgara@cnt.lispa.it>, Giorgio Cangioli <giorgio.cangioli@gmail.com>, Gareth Woodham <Gareth.Woodham@apotekensservice.se>, Konstantine Hypponen (finland) <konstantin.hypponen@kela.fi>, Kostas Karkaletsis <k.karkaletsis@gnomon.com.gr>, Répás, Norbert <norbert.repas@elga.gv.at>, Stéphane Spahni <stephane.spahni@hcuge.ch>, arnaud gaudinat <arnaud.gaudinat@hesge.ch>, Ivo Pinheiro <ivo.pinheiro@iuz.pt>, Licínio Mano <licinio.mano@iuz.pt>Dear Jörg Caumanns, Sören Bittins
The OpenNCP team is about to start implementing the new specifications for Audit Messages and we need some clarification on the following items
- The new specifications for Event details (ID's, Names) do not clarify which transaction / document is involved (e.g. "XCA::CrossGatewayQuery" now replaces "epsosPatientService::List" and "epsosOrderService::List", therefore it is not possible to distinguish them)) - is there any information present in the audit message that allows to distinguish which document was involved?
- That also applies to the provision of data - with the new "ITI-41" event ID, we only have the "XDR::ProvideandRegisterDocumentSet-b" event name, therefore both dispensation and HCER services will produce the same audit message.
Thank you very much for your attention.
Best Regards,
--
Marcelo Fonseca
epSOS - Portuguese Technical Team
- ++++++++++++++++++++++
- ++++++++++++++++++++++
- [in Progress] Clarification on the status from the - epSOS 2.0 Services Messages Validators