20130430 - Meeting minutes, Thuesday , April 30th, 2013
OpenNCP Weekly Sprint Meeting
30 APR 10:00 to 15:00 CET
Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?) Completed
Release date: 25March (Monday) > OpenNCP 2.0.0 > Postpone
5º Sprint: 25Mar > 8Apr (2 weeks) Completed
Release date: 10Apr (Thursday) > OpenNCP 1.1.2 > in Progress (Release Notes)
Release date: 11Apr (Thursday) > OpenNCP 2.0.0 > Postpone
6º Sprint: 22Apr> 3May (2 weeks) in progress
Release date: 8May (Thursday) > OpenNCP 1.1.3
7º Sprint: 6May> 17May (2 weeks)
Release date: 22 May (Thursday) > OpenNCP 2.0.0
Agenda
1. OpenNCP 1.1.3 - Progress report
2. OpenNCP 1.1.3 - Quality Assurance
3. OpenNCP 1.1.3 - Release Process
Location
Skype (sirLicman) + EtherPad (http://openetherpad.org/ubx6whW9f2)
Participants:
Aarne Roosi <Aarne.Roosi@affecto.com>,
Alexander Berler <a.berler@gnomon.com.gr>,
Anders Nyström <Anders.Nystrom@apotekensservice.se>,
Arnaud Gaudinat <arnaud.gaudinat@hesge.ch>,
Fredrik Dahlman <fredrik.dahlman@cag.se>,
[yes] Gareth Woodham <Gareth.Woodham@apotekensservice.se>,
Gergely Heja <heja.gergely@eski.hu>,
Giorgio Cangioli <giorgio.cangioli@gmail.com>
[yes] Ivo Pinheiro <ivo.pinheiro@iuz.pt>,
[yes] Konstantin Hypponen <konstantin.hypponen@kela.fi>,
[yes] Kostas Karkaletsis <k.karkaletsis@gnomon.com.gr>,
[yes] Licinio Mano <licinio.mano@iuz.pt>,
Marcello Melgara <Marcello.Melgara@cnt.lispa.it>,
Mate Beštek <mate.bestek@gmail.com>
[yes] Marcelo Fonseca <marcelo.fonseca@iuz.pt>,
[yes] Mika Myllyvirta <mika.myllyvirta@kela.fi>,
Mindaugas Ajauskas <mindaugas.ajauskas@lispa.it>,
[yes] Norbert Repas <norbert.repas@elga.gv.at>,
Patrick Ruch <Patrick.Ruch@unige.ch>,
Tomaz Cebular <Tomaz.Cebular@ivz-rs.si>
Steen Manniche <STMA@ssi.dk>,
Stefan Gustafsson <stefan.gustafsson@callistaenterprise.se>,
Stéphane Spahni <stephane.spahni@hcuge.ch>,
MEETING NOTES
1. OpenNCP 1.1.3 - Progress report (bug fixing and improvement)
- [LKM] There are no Blocker or Critical issues that may imped the 1.1.3 Release.
- [LKM] Team members should focus on: 1) Close issues in Quality Control; 2) Resolve and close In Progress issues; 3) If possible, pick up MAJOR issues.
2. OpenNCP 1.1.3 - Quality Assurance (automation strategy)
- Code Freeze - May 6th - 09h00 CET;
-- [Ivo] a) Update the versions; b) push changes to google code; c) Share artefacts;
-- [Team] d) Start QA stage: Gareth available; Kostas available only in the 7th; Konstantin/Mika will also test;
--- QA Stage should May 7th - 18h00 CET
--- Open issues during QA stage should must have a Critical priority
-- [Ivo] e) Release 8th May - 10:00 CET
[Norbert] Discuss PoC > We need to discuss (or we need to clarify) some organisational discrepancies between:
- D3.C.1 Appendix-B - Proof of Concept Testing Strategy Details (Test Levels & Phases) & First draft of an OSS road map, regarding an improved test strategy for the released components.
- Automated tests to be included in the next sprint/release from the OpenNCP.
3. OpenNCP 1.1.3 - Release Process (version preparation)
-- [Ivo] e) Release 8th May - 10:00 CET
NEXT Steps
- [To Do - Licinio] Schedule 'next' meeting - proposed date May 7, 2013, 10h00 CET