20130917 - Meeting minutes, Tuesday, September 17th, 2013

OpenNCP Weekly Sprint Meeting

17th September 15:00 to 16:30  CET

Work RoadMap - epSOS 2 Services

1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) Completed

5º Sprint: 25Mar > 8Apr (2 weeks) Completed 

6º Sprint: 22Apr> 3May (2 weeks) > Completed 

 7º Sprint: 6May> 17May (2 weeks)  > Completed

 8º Sprint: 20May> 31May (2 weeks)  > Completed

 9º Sprint: 3June> 14June (2 weeks)  > Completed

10º Sprint: 24June > 19July (4 weeks)  > in Progress

  • Release OpenNCP 2.0.1 > 31 July, 2013 (Wednesday) 6th August

ROADMAP

 

 [in progress]          OpenNCP V2.0.2                      2013-09-10?2   Transformation Manager + Emergency Scenario + Bug Fixing       
          OpenNCP V2.0.3 (after PPT)   2013-10-02   OPERATION   Ready for: PAC + HCER epSOS 2 Services   

 

          OpenNCP V2.1.0                      2013-10-30   PPT Ready for: MRO + TSAM-sync (adaptation for CTS2 compliance)       

          OpenNCP V2.1.1 (after PPT)   2013-12-05   OPERATION   Ready for: ?? 

 

Agenda

a) Roadmap & next steps planning

b) Specification presentation (MRO + TSYM Adaptation)

Location

Skype (sirLicman) + Jira Board + MeetingWords (http://meetingwords.com/GIyj3Jz3QO)

Participants:

Aarne Roosi <Aarne.Roosi@affecto.com>, 
Alexander Berler <a.berler@gnomon.com.gr>, 
Arnaud Gaudinat <arnaud.gaudinat@hesge.ch>,
Belani Hrvoje <Hrvoje.Belani@hzzo.hr>,
Fredrik Dahlman <fredrik.dahlman@cag.se>,
[yes] Gareth Woodham <Gareth.Woodham@apotekensservice.se>, 
Gergely Heja <heja.gergely@eski.hu>,
Giorgio Cangioli <giorgio.cangioli@gmail.com>,
Ljubi Igor <Igor.Ljubi@hzzo.hr>,
[yes] Ivo Pinheiro <ivo.pinheiro@iuz.pt>, 
[yes] Juergen Wehnert <juergen.wehnert@gematik.de>,
[yes] Konstantin Hypponen <konstantin.hypponen@kela.fi>, 
Kostas Karkaletsis <k.karkaletsis@gnomon.com.gr>, 
[yes] Licinio Mano <licinio.mano@iuz.pt>,
Marcello Melgara <Marcello.Melgara@cnt.lispa.it>,
[yes] Marcelo Fonseca <marcelo.fonseca@iuz.pt>, 
Mate Beštek <mate.bestek@gmail.com>,
Milada Kovarova <Milada.Kovarova@posam.sk>,
Mika Myllyvirta <mika.myllyvirta@kela.fi>, 
Mindaugas Ajauskas <mindaugas.ajauskas@lispa.it>, 
[yes] Norbert Repas <norbert.repas@elga.gv.at>,
Patrick Ruch <Patrick.Ruch@unige.ch>,
[yes] Per Loubjerg <consult@loubjerg.dk>,
Tomaz Cebular <Tomaz.Cebular@ivz-rs.si>,
Steen Manniche <STMA@ssi.dk>, 
Stéphane Spahni <stephane.spahni@hcuge.ch>,

 

 

 

 

MEETING NOTES

a) Roadmap & next steps planning

- OpenNCP > 2.0.2  Release occurred according planned;
-- Process accord expected;
--- OpenNCP 2.0.3 > Operation (after fixes or improvements that may arise from PPT)
--- OpenNCP 2.1.0 > Development (for MRO or TSAM adaptation related developments)
-- Dissemination activities > No need!
- PPT > Start 30 September - 11 October >
-- Registration open until 20 September;
-- FI, SW, PT > reduced test scope
-- CR, CH, IT, ES HU, LU , SL > full PPT
There is already an existent PPT 5 session at Gazelle, the participants should register their systems and actors in order to participate.
- VPN  ISSUES
-- OpenSwan software > part of FET implementation > and probably is part of the OpenNCP
--- OpenSwan implementation that epSOS community is adopting, 
--  Is LU  the only country having this problem? NO.
-- LU, ET
--  Could firewalls be the root problem? only partially, because there should be some more.
--- Could it be by the certificates? could also be part of the problem;
-- Kostas: din't found the root problem
--- face several problems in LU: 
---- LU can initiate connections;
---- LU cannot accept connection;
--- Task force is a good idea, but we should stop the endless email threads on the subject, centring the knowledge into a single consultation point.
---- matrix with problems
----- This page should be disseminated 
--- LKM: the issue on Jira and the confluence page
Names mentioned for the task force int toeday's TPM:  Licinio, Sören, Massi, Konstantin, Eric and generally there may be some as yet unknown resources with the NECP.
epSOS PPT - VPN setup
"As we are not using NSS stuff"...?
- Are this VPN setup instruction, up to date? ask Eric?
Schedule meeting for Friday  10hCET

b) Specification presentation (MRO + TSYM Adaptation)

- Availability of specifications:
- Maturity of specifications: 
-- Juergen will check with the Specification Work Group the status from this information;
Schedule meeting for Tuesday - 24th September  10hCET


NEXT Steps

- [Licínio] Prepare VPN issues knowledge gathering, PNs status, issue diagnose and resolution proposition (send to Juergen for share with every NEPC);
- [Licinio] Schedule OpenNCP-VPN Group - NEXT MEETING - 20 September, 10h00 CET

- [Jurgen] Gather MRO and TSAM Adaptation specification availability and maturity, for sharing with the OpenNCP development team;

- [Licinio] Schedule OpenNCP - NEXT MEETING - 24 September, 10h00 CET