20130214 - Meeting minutes, Thursday , February 14th, 2013
OpenNCP / Sprint Planning Meeting / Sprint 2 - epSOS 2 Services
2013-02-14 / 10h00 CET to 11h00 CET
OpenNCP2.0 Development RoadMap
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks)
3º Sprint: 29Fev > 8Mar (2 weeks)
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?)
- Release date: 25March (Monday) > OpenNCP 2.0.0
-- Release Notes
Today Agenda
- Sprint "Weekly" Progress Meeting
Participants:
- Licinio Mano
- Fredrik Dahlman
- Konstantin Hyppönen
- Marcelo Fonseca
- Kostas Karkaletsis
- Arnaud Gaudinat
- Gareth Woodham
1. Sprint "Weekly" Progress Meeting
- Support
Konstantin, Marcelo: provided feedback on issue solving.
There still are some more known issues that should be addressed in order to prepare the 1.1.1 release before the next PPT.
If someone is free from specifications or development, please dig in! - Specifications and Design
- PAC: Marcelo provided an overview about the update and consolidation that has been made in the specification page.
- HCER: Konstantin provided an overview about the update and consolidation that has been made in the specification page.
- MRO: was not possible due to lack of knowledge, Steen should be the best man for doing it.
- Semantic: Arnaud provided an detailed situation point regarding specifications and clarification needed.
- Development
- PAC: Marcelo provided an subtasked overview about the implemntation needed and it has been given GREEN light to proceed with the implementation.
Together with Kostas, they will start the implementation needed.
Regarding semantic inthe PAC service, Marcelo and Arnaud will combine efforts (right after this meeting) - HCER: Konstantin has statted that the implementation was already rolling
- Semantic: Arnaud refered that there is an meeting schedule for clarifying some doughs KT 1.4.10 CTS2 Services [Feb 15th - 14.00-15.30 CET]
- PAC: Marcelo provided an subtasked overview about the implemntation needed and it has been given GREEN light to proceed with the implementation.
NEXT Steps
- [done] Publish today meeting notes
- [OpenNCP Community] CONSOLIDATE Specifications and Implementation Design of: PAC, HCER, MRO, Semantic Revision
- [OpenNCP Community] CONTINUE development (PAC, HCER)
- [done] Schedule: Next Scrum Meeting: 20th Fev - 10h00 CET (project place)