20130305 - Meeting minutes, tuesday , Mar 5th, 2013
OpenNCP Development Weekly Status meeting
5 Mar 10:00 CET
Work RoadMap
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > WE ARE HERE
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?)
- Release date: 25March (Monday) > OpenNCP 2.0.0
-- Release Notes
Agenda
1. OpenNCP 1.1.1 Release - issue on delivering artefacts on JoinUP
2. OpenNCP 2.0.0 - Implementation
3. OpenNCP Community related concerns
Discussion
1. OpenNCP 1.1.1 Release - issue on delivering artefacts on JoinUP
Issue rationale: probably related with lack of disk space;
Steen: is is close contact with JoinUP support Team, in order to solve the issue and publish artefacts - ASAP - maybe tomorrow 5March.
One important note about this issue: not having the the artefacts published on JoinUP does not BLOCK the work for the 3rdPPT slot.
It doesn't BLOCK because the countries that aim to use the OpenNCP 1.1.1 in the 3rdPPT slot (PT, SW, EE, FI, etc), are able to get the code directly from the source code repositories.
2. OpenNCP 2.0.0 - Implementation
2.1 PAC
[Marcelo]
No progress, due to 3rdPPT-slot preparation;
[Kostas]
What has been done
A new portlet named "Patient Access"
PAC issues
Declaration of a new role for Patient and a set of permissions in NCP-A part
Portal Configuration to use this role during HCP Assertion and TRCA
All other issues have been developed and pushed to develop branch
How to configure portal to use custom user fields
2.2 HCER
IMPEDED by the need of "Clarifications"
Meeting request: Organize a conference about HCER semantic clarifications
2.3 MRO
SUSPENDED by lack of resources
It will not be included in the OpenNCP 2.0.0.
3. OpenNCP Community related concerns
3.1 Lack of resources - for the next 3 weeks
3rd PPT Slot - concerts and preparation;
Fewer PN involved in order to pilot epSOS 2 Services
3.2 Release date for OpenNCP 2.0.0 - 25 March
MAY not be accomplished, due to the lack of resources stated in the previous point.
It SHOULD focus on the PAC service.
HCER specifications should be clarified for the next sprint, for continue the development;
MRO specifications should be in place for start development - development is SUSPENDED for now;
3.3 Test tools for OpenNCP 2.0.0 - PAC Service
It has been communicated with Mustafa, as suggested: Communicate with IHE and Mustafa and/or epSOS TPM/PSB in order to plan the development of testing tools for epSOS 2.0 services.;
[MUSTAFA] Said that he is pushing with the IHE Team, and it is hoped that tools could will be available for the 4th PPT-Slot - after Istanbul;
NEXT Steps
- [To Do - Steen] Keep close connection with JoinUP team, in order to solve the issue on publishing the artefacts;
- [To Do - OpenNCP Community] Continue Developments - Focused in the PAC service
- [To Do - Marcello Melgara] Organize a conference about HCER semantic clarifications (and perhaps MRO, if possible);
- [To Do - Licinio Mano] Prepare a wiki page regarding OpenNCP 1.1 adopters (and 3rd PPT slot participants) and also OpenNCP 2.x intended adopters
- [To Do - Licinio Mano] Prepare and publish today meeting minutes;
- [To Do - Licinio Mano] Schedule Sprint 'Review/Retrospective/Planning' meeting - proposed date March 11, 2013, 10h00 CET