OpenNCP Weekly Sprint Meeting
9 APR 10:00 to 11:00 CET
Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?) Completed
- Release date: 25March (Monday) > OpenNCP 2.0.0 > Postpone
5º Sprint: 25Mar > 8Apr (2 weeks) Completed
Release date: 10Apr (Thursday) > OpenNCP 1.1.2 > in Progress (Release Notes)
Release date: 11Apr (Thursday) > OpenNCP 2.0.0 > Postpone
Agenda
1. OpenNCP 1.1.2 - Code Freeze
2. OpenNCP 1.1.2 - QA Assessment
2. OpenNCP 1.1.2 - Release Process
Location
Skype (sirLicman) + EtherPad (http://openetherpad.org/ck4KB5LS8T)
Participants:
MEETING NOTES
1. OpenNCP 1.1.2 - Code Freeze
- No Blocking ISSUES;
- No Critical ISSUES
-- CODE FREEZE? YES!!!
2. OpenNCP 1.1.2 - QA Assessment
Gareth: reinforce the principle/good practice that the QA stage should be shared by every member in the community (at least while we don0t have a QA focused team) and automated when possible)
- Ivo: prepares the release - and share artefacts with Gareth and Kostas;
- Gareth: Proceed (during 9 April) with QA Stage for eP/eD!
- Kostas: Proceed (during 9 April) with QA QA Stage for PS-A & B!
-- Gareth & Kostas: will report to Ivo the result of the QA stage.
--- with 2 YES > Ivo will Release 1.1.2 for JoinUp;
--- with 1 YES > Ivo will evaluate the severity from the issues found;
--- with 0 YES (2 NO) > Ivo will suspend the release and Licinio will regroup team effort around issues that need to be addressed before releasing;
AUTOMATE QA (Norber & Marcelo Fonseca have started work on this, there is work to do that should be added for the next sprint)
- Integration of CI Environment With Gazelle Services
3. OpenNCP 1.1.2 - Release Process
- Ivo: will be responsible for releasing OpenNCP 1.1.2 Artefacts for JoinUP;
- Licinio: will be responsible for the release notes on the OpenNCP 1.1.2 (Jira release and email sharing)
- Ivo: After releasing 1.1.2 prepare the source repositories for get developments commits regarding 1.1.3 - that may happen during PAT and the week after (from Apr 15 to 26).
NEXT Steps
- [To Do - Ivo + Steen] OpenNCP 1.1.2 Release 10 April > Announced
- [To Do - OpenNCP] epSOS Istanbul IHE PAT (OpenNCP supportive nations FI as eD/eP and PT as PS-A&B) from 15 to 19 April
- [To Do - Licinio] Plan > Re-start developments from 22April forward - 23rd meeting!
- [To Do - Ivo + Steen] OpenNCP 1.1.3 Release 30 April (suggestion)
- [To Do - Ivo + Steen] OpenNCP 2.0.0 Release ?? May (requires planning)
- [To Do - Licinio] Schedule 'next' meeting - proposed date Apr 23, 2013, 10h00 CET