20160315 - Meeting minutes, Tuesday 15th March 2016 - IHE preparation readiness to April CAT

20160315 - Meeting minutes, Tuesday 15th March 2016 - IHE preparation readiness to April CAT

  1. Non-repudiation => Need to register the test

  2. SMP/SML => Need to register the test

OpenNCP liaison with IHE.

Mar 15, 2016 

Estimated: 09:00 to 10:00 CET.

Performed: 09:00 to 10:00 CET.

Agenda:

  1. House Keeping

  2. Plan joint effort towards IHE CAT on the 11th and 15th of April

    1. Countries registered;

    2. Tests to be performed;

      1. eID related questions.

    3. MS Preparation activities 

    4. Monitors for testing

  3. Next Steps

Location:

  • AdobeConnect:

http://ec-wacs.adobeconnect.com/openncp/
Room Passcode:  Ask if necessary michele.foucart or markus.kalio
------------------------------------------------------------------------------------------------
If you have never attended an Adobe Connect meeting before:
Test your connection: http://ec-wacs.adobeconnect.com/common/help/en/support/meeting_test.htm
Get a quick overview: http://www.adobe.com/products/adobeconnect.html
Adobe, the Adobe logo, Acrobat and Adobe Connect are either registered trademarks or trademarks of Adobe Systems Incorporated in the United States and/or other countries.
------------------------------------------------------------------------------------------------

Participants:

@Licinio Kustra Mano

@Joao Cunha

Abderrazek Boufahja (IHE)

Tobias Pass (Austria, substituting Massi)

@markus.kalliola

@michele.foucart

Meeting Notes:

IHE 2016 CAT  -  11-15 April 2016 (Bochum, Germany)   http://www.ihe-europe.net/connectathon/cat-2016

  • What can be tested?

    • December: we tested the eID, but the Change Proposal was not delivered in time. but due to lack of participation in the EXPAND maintenance shop calls, the CP did not reach the quorum to be evaluated. And IHE only tests specifications at connectathon (that's how IHE works). This is the reason why we had only a spreadsheet.

    • February: DG Sante is taking over the the CP that can be incorporate in the Specifications;

    • April: 

      • eID Level 3;

      • More MS testing the eID;

 

Next Steps:

Follow-up meeting Mar 29, 2016 10 am CET