OpenNCP Sprint 'Review/Retrospective/Planning'

11 Mar 10:00 CET

Work RoadMap

1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) > WE ARE HERE (<- both weeks, or perhaps just the last week could be the code freeze?)
- Release date: 25March (Monday) > OpenNCP 2.0.0
-- Release Notes

Agenda

1. OpenNCP 1.1.1 Release - issue on delivering artefacts on JoinUP
2. OpenNCP 2.0.0 - Implementation
3. OpenNCP Community related concerns

Discussion

1. OpenNCP 1.1.1 Release - issue on delivering artefacts on JoinUP

  • ...

2. OpenNCP 2.0.0 - Implementation

2.1 PAC

[Marcelo]

  • No progress, due to 3rdPPT-slot preparation;

[Kostas]

What has been done

  • A new portlet named "Patient Access"

PAC issues

  • Declaration of a new role for Patient and a set of permissions in NCP-A part
  • Portal Configuration to use this role during HCP Assertion and TRCA
  • All other issues have been developed and pushed to develop branch

2.2 HCER

IMPEDED by the need of "Clarifications"

  • Meeting request: Organize a conference about HCER semantic clarifications

2.3 MRO

SUSPENDED by lack of resources

  • It will not be included in the OpenNCP 2.0.0.

3. OpenNCP Community related concerns

3.1 Lack of resources - for the next 3 weeks

  • 3rd PPT Slot - concerts and preparation;
  • Fewer PN involved in order to pilot epSOS 2 Services

3.2 Release date for OpenNCP 2.0.0 - 25 March

  • MAY not be accomplished, due to the lack of resources stated in the previous point.
  • It SHOULD focus on the PAC service.
  • HCER specifications should be clarified for the next sprint, for continue the development;
  • MRO specifications should be in place for start development - development is SUSPENDED for now;

3.3 Test tools for OpenNCP 2.0.0 - PAC Service

  • It has been communicated with Mustafa, as suggested: Communicate with IHE and Mustafa and/or epSOS TPM/PSB in order to plan the development of testing tools for epSOS 2.0 services.;
  • [MUSTAFA] Said that he is pushing with the IHE Team, and it is hoped that tools could will be available for the 4th PPT-Slot - after Istanbul;

NEXT Steps

- [To Do - Steen] Keep close connection with JoinUP team, in order to solve the issue on publishing the artefacts;

- [To Do - OpenNCP Community] Continue Developments - Focused in the PAC service 

- [To Do - Marcello Melgara] Organize a conference about HCER semantic clarifications (and perhaps MRO, if possible); 

- [To Do - Licinio Mano] Prepare a wiki page regarding OpenNCP 1.1 adopters (and 3rd PPT slot participants) and also OpenNCP 2.x intended adopters  

- [To Do - Licinio Mano] Prepare and publish today meeting minutes; 

- [To Do - Licinio Mano] Schedule Sprint 'Review/Retrospective/Planning' meeting - proposed date March 11, 2013, 10h00 CET