OpenNCP / Sprint Planning Meeting / Sprint 2 - epSOS 2 Services
2013-02-14 / 10h00 CET to 11h00 CET
OpenNCP2.0 Development RoadMap
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks)
3º Sprint: 29Fev > 8Mar (2 weeks)
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?)
- Release date: 25March (Monday) > OpenNCP 2.0.0
-- Release Notes
Today Agenda
1. Sprint "Weekly" Progress Meeting
Participants:
- Licinio Mano
- Fredrik Dahlman
- Konstantin Hyppönen
- Marcelo Fonseca
- Kostas Karkaletsis
- Arnaud Gaudinat
- Gareth Woodham
1. Sprint "Weekly" Progress Meeting
- ...
NEXT Steps
- [done] Publish today meeting notes
- [OpenNCP Community] CONSOLIDATE Specifications and Implementation Design of: PAC, HCER, MRO, Semantic Revision
- [OpenNCP Community] CONTINUE development (PAC, HCER)
- [done] Schedule: Next Scrum Meeting: 20th Fev - 10h00 CET (project place)