OpenNCP Community: Weekly meeting

21th 21st July 14:30 to 16:00  CET 

...

  • TCon technologies
    • GoToMeeting..... in a trial mode > Go to License version (36€ per month).
      • PARENT (Nacionalni Institut za Javno Zdravje) provided a license for 1 organizer.
        • Many thanks to @Matic Meglic

  • Code repositories
    • Now on BitBucket after migration from Google Code.
      • Are the Google Code repositories Open (allowing code push and commit)?
        • NO, they are BLOCKED;
      • Where are the instructions, for new comers, on where should they go to push code?
  • CI Migration - Developments
    • Requirements document that is being used for setting up the new infrastructure
      • Infrastructure (requirements document) is being set up, so  that the migration work start.
        • Procurement is taking longer than expected, 
          • Planned date for availability 28th of July
            • New DATE foreseen: end of September
        • Migration works should be postponed.
          • Orchestrate with iUZ work "time baseline" 
          • Isabel Cruz: shared that there is no problem on the delay, but SPMS should provide a two week warning on infrastructure availability, so that iUZ team can prepare themselves.

...

  • Specification and Design:
      • Complementary to STORK (Stork used in a more centralized services architecture, while FuruteID is more local seamless services).
  • Next events:
    • e-SENS 
      • Work meeting: 10 to 12 of September... discuss and validate the e-SENS eID component;
        • Having some of your team members attending e-SENS meeting on the 10 to 12 of September?
      • September 2014: Countries need to commit specifically to what countries want to Pilot.
      • Wave 1 for eHealth Pilots: Start piloting: 2015, April;
    • STORK 
      • Developments Effort Estimation (for UC1, UC2, UC3) DONE (end of July, by iUZ and Gnomon);
        • Educated guess: end of developments DEC 2014; 
      • Engagement of countries for Piloting actions (end of August);
        • Candidate countries to be contacted: AT, CH, SP, IT?, PT, GR, MT??, LU;
          • LU: confirms involvement with Stork 1 and 2, but so far we need to wait a little bit more to confirm if there will be able to pilot.
      • Probably in the next OpenNPC Meeting we can have an upDATE (28th July)

...

  •  Licinio Kustra Mano Schedule next meeting: 28st 28tht of July (Monday) from, 14:30 to 15:30 CET (60min)
  •  Licinio Kustra Mano: Update the Manifesto page with feedback after EXPAND WP5 KickOff;
  •  Licinio Kustra Mano: Obtain EXPAND WP5 Proposals towards Governance and Manifesto;
  •  Licinio Kustra Mano: Prepare a list of OpenNCP running instances, contact points;
  •  Licinio Kustra Mano: Understand more in detail where and when the e-SENS meeting will happen, so that we could have some more inputs there from the OpenNCP Consultants.

...

  •  Licinio Kustra Mano: Compile and re-assemble presentations, making them available in PDF format.
  •  Licinio Kustra Mano: Update the Athens event page with all the highlighs, so that the page can be distributed (with the PDF) for dissemination purposes. 
  •  Licinio Kustra Mano: CI proposal from eGOBLab: update Fredrik and request for advise on how to proceed;