20151014 - e-SENS eP/PS, Towards Piloting Stage - Meeting minutes: Thursday, October 14th 2015

Date

12:00 CEST

Duration: 

Agenda

1) Status Point of each MS (5min - news only)

2) Update on Progress Report (5min - news only)

3) Inputs needed for WP5 (20-30 min)

4) AOB

 

Location

T-CON tool from e-SENS WP 5.2 (audio only)

Details for connection shared by e-mail

Attendees

  • Rui Alves (PT)

  • Ioannis Petrakis (e-SENS WP5.2 Contact Person - assistant)

  • François Wisniewski (LU)

Invited Members

  •  

  • Licinio Kustra Mano (PT, Domain Pilot Architect)

  •  

  • Ortwin Donak (LU)
  • Marcello Melgara (IT)

  • Zoi (GR)

  • Dimitrios Katehakis (e-SENS WP5.2 Contact Person)

  • João Gonçalves (PT)

  • Alexandre Santos (PT)

  • Stathis Andronikos (GR)

  • George Pangalos (GR)
  • Samuel Danhardt (LU)
  • Heiko Zimmermann (LU)
  • Maria Jesús Macías (ES)

  • Celia Varela (ES)

  • Julio Francisco (ES)

Goals

  • Overview on the progress of each MS towards the Piloting Stage
  • Discuss technical/non-technical issues identified by each MS
  • Prepare inputs for WP5

Related Documents

 

Discussion items

0) CONTEXT

MS PILOT AIMS?

      • Greece (eP-B - later PS-A - PS-B is possible), 
      • Luxembourg (PS-B, )
      • Spain (PS-A , PS-B is possible)
      • Portugal (PS-A/B)
      • Italy (eP-A, PS-A... PS-B is possible)

1) Status Point of each MS:

GR UPDATE:

      • CURRENT WEEK:
          • No updates.


LU UPDATE:

      • CURRENT WEEK:
          • Preparing the NCP with 2.3.0 for EXPANDATHON.
          • Country-B.
          • Country-A simulated - but not with real PS in the NI.
          • Building NC

 


PT UPDATE :

  • CURRENT WEEK:
    • GR and PT established connection to allow PS exchange.
    • PT and LU able to exchange ionformation.

 

IT UPDATE:


  • IN THE LAST CALL: 
  •  e-SENS eP/PS WP 5.2 (yesterday) PPT and OP - Lombardy

    DEBUG eID L1 - LARMS - 2.3.0 RC-1 with Italy Cards
    Fix the problem with medicinal descriptions;


  • We have installed in PPT and OP OpenNCP 2.2.0. We are working with Soeren to debug the Larms eID (level 1) because Italian Card was not compliant. 2.3.0-RC-1 to have included the Italian Card.
    We are working to sort out the problem of medicinal descriptions and updating MVC to 2.0; 

    • Mapping ICD9 to ICD10 (MVC 2.0).

        • Licinio: agree: this is an open issue.
        • We will have a conference call with Italian... to share a mapping to find a joint solution.
        • MVC is closed and available (EN and IT)
        • We have to work on this issue:
          • ICD9 mapping to ICD 10 is something related with PT, IT and ES
          • It must be correctly adressed maybe with support of EXPAND Semantic Main Shop.

 

About the issue of Medicinal Descriptions and mapping ICD 9 to 10 (MVC 2.0):

Licinio Kustra Mano: Issue for eP and not PS - Marcello Melgara: to confirm this.

 

 

ES UPDATE :


 

2) Progress Report Update:

Goal: Send (until 25th Sept) an updated version of the Progress Report with relevant information/updates from last weeks.

Template:

Previous reports and more on BSCW: 

So far (14th Oct) we've received:

    • LU
    • PT
    • GR
    • ES (no updates yet)
    • IT (check if missed, or ask Marcello)

We will upload them in the BSCW.

 

3) Request for feedback to WP5

3.1 - Request for Domain Pilot Architect (LKM)

3.1.1 Material - documentation on testing procedures - Rui Alves (Unlicensed): engage with Licinio about this and provide the materials we have so far. Mitigation Strategy to be checked.

3.1.2 Names of members to create access to JIRA (Domain + MS) - 

One person from domain and one (or two) person from each MS: 

Technical persons - or at least Contact Architects

 

3.2 - Legal issues tracking

Lack of national eID framework for MSs

Lack of eHealth Temporary Legal Agreements (TLAs)

Use limitations imposed by SDOs that rule some of the terminologies and code sets

Not having the proper legal environment set up for elevating pilots and its technology into routine operation

Lack of agreement to use Central Services during the course of the project

 

@François: It's a decision to take and we will have to take it soon. Think of re-planning the pilot.

@François: Not sure about point 1 is a legal issue. Maybe a technical issue.

@François: EXPAND created a TLA to deliver to eHN?? Marcello should be aware of this. PT has signed, LU I think yes (one to one and not one to N), GR not sure.

 

 

3.2.1 - Add/remove/change any?

3.3 - ABB Readiness Monitoring

File here: e-SENS WP5.2.1 Use of BBs_v0.71.xlsx

François: SMP/SML - Orange

eID: Not sure about the ABBs names and how they relate with the eID Levels... We don't have Authentication. 

Non-Rep: It is ok about Conformance tested, and it should be green for countries.

 

 


 

4) AOB