OpenNCP Weekly Sprint Meeting
22nd October 10:00 to 12:00 CET
Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) Completed
5º Sprint: 25Mar > 8Apr (2 weeks) Completed
6º Sprint: 22Apr> 3May (2 weeks) > Completed
7º Sprint: 6May> 17May (2 weeks) > Completed
8º Sprint: 20May> 31May (2 weeks) > Completed
9º Sprint: 3June> 14June (2 weeks) > Completed
10º Sprint: 24June > 19July (4 weeks) > Completed
- Release OpenNCP 2.0.1 >
31 July, 2013 (Wednesday) 6th August - Release OpenNCP V2.0.2 > 2013-09-12 Transformation Manager + Emergency Scenario + Bug Fixing
5ª PPT [in progress]
- OpenNCP V2.0.3 (after PPT) 2013-10-16 OPERATION Ready for: PAC + HCER epSOS 2 Services
11º Sprint: 15Oct > 28Oct (2 weeks) [plan]
- OpenNCP V2.1.0 2013-10-30 PPT Ready for: MRO + TSAM-sync (adaptation for CTS2 compliance)
??ª PPT [recommended]
- OpenNCP V2.1.1 (after PPT) 2013-12-05 OPERATION Ready for: ??
AGENDA
a) 5º PPT slot - retrospective and lessons learned
b) Dev Sprint Progress Monitoring
- Sprint Accomplishments - so far;
- Impediments - to clean
- Re-focus work for this week
LOCATION
- Skype (marcelo.fonseca.iuz) + Jira Board + MeetingWords ()
PARTICIPANTS
Today's Meeting Participants:
Members List:
MEETING NOTES
a) 5º PPT slot - retrospective and lessons learned
-- What is the current status?
[ MF ] No additional bugs were reported and all the remaining were solved;
-- Should we move forward with the release of OpenNCP 2.0.3? Any impedments?
[ MF ] Apparently the OpenNCP 2.0.3 is ready for release.
[ KH ] Wait for final report of PPT5 and then perform the release;
[ MF ] We did not got the final confirmation about PPT finish;
b) Development Sprint Progress Monitoring (MRO)
-- What is the current status? Any impedments?
[ MF ] NCP-A tasks are ready and in QA status;
[ MF ] NCP-B tasks are ready and in QA status;
[ KK ] The Portal is ready for integration testing with the OpenNCP core;
-- Additional Clarifications:
[ MF ] Check the required audit messages identifiers;
-- How far are we distant from the desired goal?
[ MF ] We will manage to have this service ready untill the end of the sprint;
c) Brief notes from F2F Meeting
[ LKM ] CTS2 will not be implemented;
[ LKM ] Next sprint focus will be in CI improvement;
NEXT STEPS
- [ MF ] Ask for clarification on PPT5 endup;
- [ IP ] Wait for first PPT result. (Konstantin) and then perform the release.
- [ MF ] Check the required audit messages identifiers, for MRO;
- [ MF ] Provide OpenNCP artifacts for integration testing with portal to Kostas;
- [ MF ] Schedule Next Conf -> Tuesday, 29th October 2013 10h CET ;
LAST MEETING ACTIONS
- [MF] next meeting > 29Oct > 12h00 CET > Sprint Review, Retrospective and Planning
- [IP] OpenNCP 2.0.3 Release > Reschedule for 23 October, after confirmation on TConf if no impediments found
- [MF] Missing task regarding the Audit messages, that probably could be similar to the PS with different identifiers > Ask or digging the documentation? > Let's start by reading any available documentation;
- [IP] Assess conditions for OpenNCP 2.0.3 Release, and in case of "all green" > proceed with the release.