OpenNCP Weekly Sprint Meeting
4th Jun 10:00 to 11:00 CET
Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?) Completed
- Release date: 25March (Monday) > OpenNCP 2.0.0 > Postpone
5º Sprint: 25Mar > 8Apr (2 weeks) Completed
- Release date: 10Apr (Thursday) > OpenNCP 1.1.2 > Completed (Release Notes)
- Release date: 11Apr (Thursday) > OpenNCP 2.0.0 > Postpone
6º Sprint: 22Apr> 3May (2 weeks) > Completed
- Release date: 8May (Wednesday) > OpenNCP 1.1.3 > Completed (Release Notes)
7º Sprint: 6May> 17May (2 weeks) > Completed
- Release date: 22 May (Thursday) > OpenNCP 2.0.0 (Postpone)
8º Sprint: 20May> 31May (2 weeks) > in Progress
9º Sprint: 3June> 14June (2 weeks)
- Support OpenNCP 1.1.3 (used in 4th PPT-slot as May 27th - June 7th)
- Release OpenNCP 2.0.0 > 19 June (Thursday)
Agenda
1. PAC QA Stage
2. HCER QA Stage
3. epSOS 2.0 Audit Trail EventIDs (Discussion of Roadmap)
4. 4PPT OpenNCP usage feedback
Location
Skype (Gareth > konaboy32 ) + EtherPad (http://meetingwords.com/OuTa9jb29i)
Participants:
MEETING NOTES
1. PAC QA Stage
-- The service implementation is complete.
2. HCER QA Stage
-- Model Based Validator - in the new TSAM
3. epSOS 2.0 Audit Trail EventIDs (Discussion of Roadmap)
-- The adoption of new EventIDs does not seem to bring any issue apart from the following line:
--- We need to report to the specification team that there is no information about the related transaction on each EventID (e.g. "XCA::CrossGatewayQuery" will replace "epsosPatientService::List" and "epsosOrderService::List", therefore it would not be possible to distinguish them) - perhaps it should be that way, but further clarification is needed.
4. 4PPT OpenNCP usage feedback
- Database connection leak issues
NEXT Steps
- [To Do - Licinio] Schedule 'next' meeting - proposed date June 11th, 2013, 14h30 CET
- [To-Do] MF: Ask for clarification to the specification team about the missing transaction info on Audit Messages details
- [To-Do] MF: Ask Eric for information about the HCER web-service validator.
- [To-Do] MM: Disseminate email about: "News about OpenNCP2.0.0 and request for contributions"