OpenNCP Weekly Sprint Meeting
12nd 19nd November 1009:00 30 to 1211:00 CET
Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) Completed
5º Sprint: 25Mar > 8Apr (2 weeks) Completed
6º Sprint: 22Apr> 3May (2 weeks) > Completed
7º Sprint: 6May> 17May (2 weeks) > Completed
8º Sprint: 20May> 31May (2 weeks) > Completed
9º Sprint: 3June> 14June (2 weeks) > Completed
10º Sprint: 24June > 19July (4 weeks) > Completed
- Release OpenNCP 2.0.1 >
31 July, 2013 (Wednesday)6th August - Release OpenNCP V2.0.2 > 2013-09-12 Transformation Manager + Emergency Scenario + Bug Fixing
5ª PPT [completed]
11º Sprint: 15Oct > 28Oct (2 weeks)
12º Sprint: 1Nov > 14Oct (2 weeks) [ in progress ]
...
AGENDA
- Sprint Review;
- QA Internal STAGE Planning;
- Skype (sirLicman) + Jira Board + MeetingWords ()
- Development Board: https://openncp.atlassian.net/secure/RapidBoard.jspa?rapidView=1
- Support Board: https://openncp.atlassian.net/secure/RapidBoard.jspa?rapidView=2
- Meeting Words: http://meetingwords.com/zb1ANd6ZNm
PARTICIPANTS
Today's Meeting Participants:
Invited Members List:Gareth Woodham <Gareth.Woodham@apotekensservice.se>,
Invited Members List:
...
- PN’s QA > 25Nov to 6 Dec
GOLD (FINAL) Release - OpenNCP V2.1.1
Release Process: 9 to 13Dec
Support Countries Updating: 16 to 20Dec;
- The current Gazelle validation web-services do not return any EVS Permanent link, as they only validate the messages and return validation result and details (errors and warnings);
- it would be useful to have a "permanent link" functionality (in Gazelle Remote validation services) in order to keep validation reports simpler and traceable, by linking them to validation pages in EVS Client;
- We should enforce the responsible usage of remote validation services by PN's as some limitations are imposed by IHE;
- The current imposed numbers ( No more than 30 requests per IP address per minute, No more than 3000 requests per period of 24 hours per IP address) should be enough for the CI environment and even PN's - but we should keep this topic under control;
- A meeting between Gareth Woodham, Marcelo Fonseca and Eric will take place tomorrow to discuss this topic;
[LKM]
Knowledge sharing & Collaborative Design
https://openncp.atlassian.net/wiki/display/ncp/Road+to+Sustainability
- Webinars (online) – When?
- a. Tools and Method
- b. Architecture and Technologies
- c. Testing and Deploying
- Workshop (f-2-f) – Where? When?
- a. Real Life Operation - Struggles
- b. Security Hackathon
- c. Performance Hackathon
- d. 3rd Party Projects Collaboration
- e. Designing the Future - evolutions roadmap
How can we add more value to actions?
Questions and next steps?
NEXT STEPS (include previous meeting actions needing monitoring)
Retrospective" TConf > Tuesday, 25th November 2013 09h30 CET
Previous meeting - NEXT STEPS
Status | ||||
---|---|---|---|---|
|
;
[ Ivo Pinheiro ] Prepare and make available OpenNCP 2.0.3 Release Notes - Technical DetailsStatus colour Green title Done
[ Licinio Kustra Mano ] Announce OpenNCP 2.0.3 ReleaseStatus colour Green title Done
[ Marcelo Fonseca ] CI Environment > Clarify with Eric Poiseau the OpenNCP CI Requirements and Strategy > having in mind the sustainability plan for this service;Status colour Green title DONE Status colour
Green title
[ Marcelo Fonseca and Gareth Woodham ] Focus TConf on "Suite Enhancements" design refinement and development work organization + effort estimation + Implement Enhancements;DONE Status colour
Green title
[ Marcelo Fonseca and Gareth Woodham ] Implement the "Suite Enhancements"DONE
[ Ivo Pinheiro ] Research for alternatives approaches to - e.g. cloud based services with Open Source Projects special service plans.Status colour Red title ON HOLD
[ Licinio Kustra Mano ] Request Kostas Karkaletsis to report (OpenNCP Support Board) issue found related with MRO new service (Status colour Yellow title IN PROGRESS
[ Licinio Kustra Mano ] Create Draft:Status colour Green title DONE Status colour
Green title
[ Licinio Kustra Mano ] Create Draft: ;DONE Status colour
Yellow title
[ Licinio Kustra Mano ] Create Draft:IN PROGRESS Status colour
Green title
[ Licinio Kustra Mano ] Circulate for review in OpNCP-Comm (Stéphane Spahni and Ivo Pinheiro and Konstantin Hyppönen) for Review:DONE Status colour
Yellow title
[ Licinio Kustra Mano ] Circulate for review in OpNCP-Comm (Stéphane Spahni and Konstantin Hyppönen) for Review: ;IN PROGRESS Status colour
Yellow title
[ Licinio Kustra Mano ] Circulate for review in OpNCP-Comm (Stéphane Spahni + Konstantin Hyppönen + Ivo Pinheiro) for Review:IN PROGRESS Status colour
Green title
[ Licinio Kustra Mano ] OpenNCP Webinars > Present a value proposition (to OpenNCP-Comm and to Juergen);DONE Status colour
Green title
[ Licinio Kustra Mano ] OpenNCP Workshop > Present a value proposition (to OpenNCP-Comm and to Juergen) for further discussion on When and How make this happen.DONE
[OpenNCP-Comm] OpenNCP Webinars & Workshop > Consolidation and ReviewStatus colour Yellow title IN PROGRESS
[ Licinio Kustra Mano ] VPN Problem > Provide a short summary of what has happened and solutions adoptedStatus colour Blue title To Do