OpenNCP Weekly Sprint Meeting

10th September 10:00 to 11:00  CET

Work RoadMap - epSOS 2 Services

1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) Completed

...

 [in progress]          OpenNCP V2.0.2                      2013-09-10   10?2   Transformation Manager + Emergency Scenario + Bug Fixing       

...

          OpenNCP V2.1.1 (after PPT)   2013-12-05   OPERATION   Ready for: ?? 

 

Agenda

a) Bug Fixing

b) Code freeze & Start Release Process (OpenNCP 2.0.2)

c) OpenNCP Promotion Documentation

Location

Skype (sirLicman) + Jira Board + MeetingWords (http://meetingwords.com/TOFksfQYCh)

Participants:

Aarne Roosi <Aarne.Roosi@affecto.com>, 

...

Fredrik Dahlman <fredrik.dahlman@cag.se>,
[yes] Gareth Woodham <Gareth.Woodham@apotekensservice.se>, 

...

Ljubi Igor <Igor.Ljubi@hzzo.hr>,
[yes] Ivo Pinheiro <ivo.pinheiro@iuz.pt>, 

...

Kostas Karkaletsis <k.karkaletsis@gnomon.com.gr>, 
[yes] Licinio Mano <licinio.mano@iuz.pt>,

...

Mate Beštek <mate.bestek@gmail.com>,
[yes] Milada Kovarova <Milada.Kovarova@posam.sk>,

...

Mindaugas Ajauskas <mindaugas.ajauskas@lispa.it>, 
[yes] Norbert Repas <norbert.repas@elga.gv.at>,
Patrick Ruch <Patrick.Ruch@unige.ch>,
[yes] Per Loubjerg <consult@loubjerg.dk>,

...

Stéphane Spahni <stephane.spahni@hcuge.ch>,

 

 

 

 

MEETING NOTES

a) Bug Fixing

Support Board Overview: https://openncp.atlassian.net/secure/RapidBoard.jspa?rapidView=2

(tick) All critical  & blockers are solved, so GREEN LIGHT for release;

b) Code freeze & Start Release Process (OpenNCP 2.0.2)

- GO!

    - OpenATNA will be the last artifact being compiled;
    - QA Stage:  Is this needed? Who will address some effort?
        - PT: Ivo
        - SE: Gareth
        - FI: ??
  • Who else is available?

Status
subtletrue
colourYellow
titleplease check next steps section for detailed release process strategy

2.0.2 Release Changelog and Notes (preview)  https://openncp.atlassian.net/wiki/x/BYBpAQ

c) OpenNCP Promotion Documentation

...

  • Installation Manual - Overview:

...


NEXT Steps

  •      NEXT MEETING - 10 September, 10h00 CET

...

- [Ivo] Prepare the release artifacts and share the for QA Stage, send an email
- [PNs available] Collaborate in the QA stage, and providing feedback about the correctness of artefacts;
- [Licinio] Check if there is any fixes that must be done before release;
- [Ivo] Proceed the release for JoinUP.
- [Licinio] Share OpenNCP- technical documentation for promotion purposes;
- [OpenNCP] Update the installation manual, regarding: OpenATNA (Gareth) + TM (Ivo);
- [Licinio] NEXT MEETING - 17 September, 15h00 CET