OpenNCP Weekly Sprint Meeting
10th September 10:00 to 11:00 CET
Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) Completed
...
[in progress] OpenNCP V2.0.2 2013-09-10 10?2 Transformation Manager + Emergency Scenario + Bug Fixing
...
OpenNCP V2.1.1 (after PPT) 2013-12-05 OPERATION Ready for: ??
Agenda
a) Bug Fixing
b) Code freeze & Start Release Process (OpenNCP 2.0.2)
c) OpenNCP Promotion Documentation
Location
Skype (sirLicman) + Jira Board + MeetingWords (http://meetingwords.com/TOFksfQYCh)
Participants:
...
...
...
...
...
...
MEETING NOTES
a) Bug Fixing
Support Board Overview: https://openncp.atlassian.net/secure/RapidBoard.jspa?rapidView=2
All critical & blockers are solved, so GREEN LIGHT for release;
b) Code freeze & Start Release Process (OpenNCP 2.0.2)
- GO!
- OpenATNA will be the last artifact being compiled;
- QA Stage: Is this needed? Who will address some effort?
- PT: Ivo
- SE: Gareth
- FI: ??
Status |
---|
subtle | true |
---|
colour | Yellow |
---|
title | please check next steps section for detailed release process strategy |
---|
|
2.0.2 Release Changelog and Notes (preview) https://openncp.atlassian.net/wiki/x/BYBpAQ
c) OpenNCP Promotion Documentation
...
- Installation Manual - Overview:
...
NEXT Steps
- NEXT MEETING - 10 September, 10h00 CET
...
- [Ivo] Prepare the release artifacts and share the for QA Stage, send an email
- [PNs available] Collaborate in the QA stage, and providing feedback about the correctness of artefacts;
- [Licinio] Check if there is any fixes that must be done before release;
- [Ivo] Proceed the release for JoinUP.
- [Licinio] Share OpenNCP- technical documentation for promotion purposes;
- [OpenNCP] Update the installation manual, regarding: OpenATNA (Gareth) + TM (Ivo);
- [Licinio] NEXT MEETING - 17 September, 15h00 CET