OpenNCP Weekly Sprint Meeting

21 21st MAY 10:00 to 11:00  CET

Work RoadMap - epSOS 2 Services

1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?) Completed

...

6º Sprint: 22Apr> 3May (2 weeks) > Completed 

  • Release date: 8May (Wednesday) > OpenNCP 1.1.3  > Completed (Release Notes)

 7º Sprint: 6May> 17May (2 weeks)  > in progressCompleted

  • Release date: 22 May (Thursday) > OpenNCP 2.0.0 (Postpone)

 8º Sprint: 20May> 31May (2 weeks)  > in Progress

  • Goal: PAC + HCER QA

 9º Sprint: 3June> 14June (2 weeks) 

  • Support OpenNCP 1.1.3 (used in 4th PPT-slot as May 27th - June 7th)
     
  • Release OpenNCP 2.0.0 19 June (

...

  • Thursday) 

 

Agenda

1. PAC Demonstration progress

2. HCER Development progress

3. Test Automation Implementation progress4. OpenNCP version merging progress (1.1.3 to 2.0.0)

 

Location

Skype (sirLicman) + EtherPad (not availablehttp://meetingwords.com/lZNM9WECpb)

Participants:

Aarne Roosi <Aarne.Roosi@affecto.com>, 

...

[yes]Stéphane Spahni <stephane.spahni@hcuge.ch>,

 

 

MEETING NOTES

1. PAC Demonstration progress

- [MF] Demonstration IMPEDED: 

...

-- ACTION: Wait for Pavol contact in order to restart the services - currently down (https://support.epsos.cz/issues/303);

 


2. HCER Development progress

-- [MM - minor Impediment] The TM and TSAM (PoSam) - they will be release in June 3.

3. Test Automation Implementation progress

-- ACTION: Try to schedule a meeting with Mustafa, having as framework Norbert email;
- [LM] Unfortunately there was no member available for implement  the "Test Automation" mechanisms.

...


[MM] Already available: Schematron and Model Base validator: MRO and HCER
[Kostas] PT-187 and PT-189: Moved to QA
[Konstantin & Fonseca] HCER - 1st) Needs Functionality TEST and 2nd) Model Base validators;
[Norbert] Automated test should be adopted at this stage, regarding that Model Base validators for the HCER are already in place;

-- ACTION-1: [Norbert] Assure with Eric that the services from Gazelle are ready for integration and sustainability; (The most important task is guaranteeing the availability of the Gazelle test services during and beyond the lifetime of the epSOS)
-- ACTION-2: [MF] Start FUNCTIONAL TEST;
-- ACTION-3 (after action-1 DONE): [MF] Start automated TEST implementation with Model Base validators;

3. OpenNCP version merging progress (1.1.3 to 2.0.0)

- [IP] Request for comments - ASAP Tasks proposal:
    1. Merge branch release/1.1.3 with develop development branch (TODO ASAP)
    2. If critical issues need to be solved it will be created an hotfix branch from master to fix this issues.
    3. This should be the strategy to be used from now on:
        --  For the critical issues: should be created an hotfix branch that, after the issues are solved should be merged with master branch and develop branch.
        --  For new features/developments: the new developments should be made on the develop branch.
- [LKM] The merge will occur in the beginning of the next week: 21 and 22 May.
. Create a branch release/1.1.4 solve the issues that eventually occur during the 4th PPT slot (This will be the last branch created for support in the 1.X.X OpenNCP)
3. Release the OpenNCP 1.1.4 after 4th PPT slot
4. Merge release/1.1.4 with development branch
5. Release OpenNCP 2.0.0

 

4. OpenNCP 2.0.0 Release Date

- [Mustafa] 4th PPT-slot as May 27th - June 7th. > epSOS 1 Services;
- [MM] Post-Pone OpenNCP 2.0.0 Release > for QA purposes;
- [LKM] Best date for OpenNCP 2.0.0 Release: June 18th;

 

 

 

NEXT Steps

- [To Do - Licinio]  Schedule 'next' meeting - proposed date May 28st, 2013, 10h00 CET

- [To Do - Gareth] Discussion point for next meeting: - Move epSOS-Web to a different TaskBoad;