OpenNCP Weekly Sprint Meeting
14 MAY 14:30 to 15:30 CET
Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?) Completed
...
- Release date: 22 May (Thursday) > OpenNCP 2.0.0 (planned)
Agenda
0. Monitor previous meeting "next steps"
...
4. OpenNCP version merging progress (1.1.3 to 2.0.0)
Location
Skype (sirLicman) + EtherPad (http://openetherpad.org/bhaxTvYuuc)
Participants:
...
MEETING NOTES
0. Monitor previous meeting "next steps"
- [Done - OpenNCP] Review in QA issues, regarding support board (https://openncp.atlassian.net/secure/RapidBoard.jspa?rapidView=2) they will be included in the OpenNCP 1.1.3 ...
- [Done 7May - Licinio] Schedule next meeting - proposed date May 14, 2013, 14h00 CET, follows meeting suggested agenda:
1. PAC Demonstration progress
- [MF] Demonstration IMPEDED:
-- ACTION: PPT Environment > Open Ticket as Incident - Priority Hight > CareCom Support
2. HCER Development progress
- [Kostas] The UI is almost closed - some screens shared (https://openncp.atlassian.net/browse/PT-187); ...
-- [MM] The TM and TSAM (PoSam) - they will be release in June 3.
3. Test Automation Implementation progress
- [Norbert] Progress: Proof of Concept? Mustafa has been contacted to join the boat for decision taken regarding automation test overview.
...
- [LM] Unfortunately there was no member available for implement the "Test Automation" mechanisms.
4. OpenNCP version merging progress (1.1.3 to 2.0.0)
- [IP] Request for comments:
...
-- [MM] The 4ºPPT > beginning June.
NEXT Steps
- [To Do - MarceloFonseca] PAC Impediment > Open Ticket as Incident - Priority Hight > CareCom Support
...