OpenNCP Gold Release Meeting

...

Work RoadMap - epSOS 2 Services

1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) Completed
5º Sprint: 25Mar > 8Apr (2 weeks) Completed 
6º Sprint: 22Apr> 3May (2 weeks) > Completed 
7º Sprint: 6May> 17May (2 weeks)  > Completed
8º Sprint: 20May> 31May (2 weeks)  > Completed
9º Sprint: 3June> 14June (2 weeks)  > Completed
10º Sprint: 24June > 19July (4 weeks)  > Completed

  • Release OpenNCP 2.0.1 > 31 July, 2013 (Wednesday) 6th August
  • Release OpenNCP V2.0.2 > 2013-09-12   Transformation Manager + Emergency Scenario + Bug Fixing      

5ª PPT [completed]

  • [NOT] OpenNCP V2.0.3 (after PPT)   2013-10-16   OPERATION   Ready for: PAC + HCER epSOS 2 Services 

11º Sprint: 15Oct > 28Oct (2 weeks) > completed 

  • PPT Ready for: MRO (new epSOS 2 Service)
  • [√] OpenNCP V2.0.3 (after PPT)   2013-11-05   OPERATION   Ready for: PAC + HCER epSOS 2 Services

12º Sprint: 1Nov > 14Oct (2 weeks) [ in progress ]  

12º Sprint: 5Nov > 19Oct (2 weeks) [ in progress ] (delayed one week due to lack of resources to work in the 1st week)

  • PPT Ready for: CI Automated Testing Suite Enhancements > COMPLETED

  • OpenNCP V2.1.0-RC0 (PPT Ready)  2013-11-20  > MRO + CI Automated Testing Suite Enhancements [DONE]


PPT/QA Stage [not a formal PPT but a more structured QA stage - coordinated by the OpenNCP Community]  

...

- ALL BLOKERS and CRITICAL issues are CLOSED
 - a.1 Global Perspective:
    - LU, FI, PT > celebrating the huge Milestone (one and half years), wishing to move forward;    -- learn


b) Documentation Quality Review

...