Work RoadMap - epSOS 2 Services
1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) Completed
5º Sprint: 25Mar > 8Apr (2 weeks) Completed
6º Sprint: 22Apr> 3May (2 weeks) > Completed
7º Sprint: 6May> 17May (2 weeks) > Completed
8º Sprint: 20May> 31May (2 weeks) > Completed
9º Sprint: 3June> 14June (2 weeks) > Completed
10º Sprint: 24June > 19July (4 weeks) > Completed
- Release OpenNCP 2.0.1 >
31 July, 2013 (Wednesday)6th August - Release OpenNCP V2.0.2 > 2013-09-12 Transformation Manager + Emergency Scenario + Bug Fixing
5ª PPT [completed]
11º Sprint: 15Oct > 28Oct (2 weeks)
12º Sprint: 1Nov > 14Oct (2 weeks) [ in progress ]
...
...
MRO Service + CI Enhancements
INTERNAL QA > 19 to 22 Nov > OpenNCP V2.1.0;
PN’s QA > 25Nov to 6 Dec
GOLD (FINAL) Release - OpenNCP V2.1.1
Release Process: 9 to 13Dec
Support Countries Updating: 16 to 20Dec;
- The current Gazelle validation web-services do not return any EVS Permanent link, as they only validate the messages and return validation result and details (errors and warnings);
- it would be useful to have a "permanent link" functionality (in Gazelle Remote validation services) in order to keep validation reports simpler and traceable, by linking them to validation pages in EVS Client;
- We should enforce the responsible usage of remote validation services by PN's as some limitations are imposed by IHE;
- The current imposed numbers ( No more than 30 requests per IP address per minute, No more than 3000 requests per period of 24 hours per IP address) should be enough for the CI environment and even PN's - but we should keep this topic under control;
- A meeting between Gareth Woodham, Marcelo Fonseca and Eric will take place tomorrow to discuss this topic;
Knowledge sharing & Collaborative Design
- Webinars (online) – When?
- a. Tools and Method
- b. Architecture and Technologies
- c. Testing and Deploying
- Workshop (f-2-f) – Where? When?
- a. Real Life Operation - Struggles
- b. Security Hackathon
- c. Performance Hackathon
- d. 3rd Party Projects Collaboration
- e. Designing the Future - evolutions roadmap
...