OpenNCP Weekly Sprint Meeting

23rd Jul 10:00 to 11:00  CET

Work RoadMap - epSOS 2 Services

1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?) Completed

...

  • Goal 1: PAC + HCER > Audit Trail Messages (Compliance)
  • Goal 2: HCER > Document Automated Tests (Quality)
  • //Goal 3: PS + PAC > Document & Transactions Automated Tests (Quality)
  • //Goal 4: eP/eD > Document & Transactions Automated Tests (Quality)

  • Release OpenNCP 2.0.1 > 31 July, 2013 (Wednesday)

 

Agenda

1. OpenNCP Support

2. OpenNCP 2.0.1 Progress

2.1 PAC & HCER Audit Trail

 

 

Location

Skype (sirLicman + Jira Board)

Participants:

Aarne Roosi <Aarne.Roosi@affecto.com>, 

...

Giorgio Cangioli <giorgio.cangioli@gmail.com>,
[yes] Ljubi Igor <Igor.Ljubi@hzzo.hr>,
[yes] Ivo Pinheiro <ivo.pinheiro@iuz.pt>, 
Konstantin Hypponen <konstantin.hypponen@kela.fi>, 
[yes] Kostas Karkaletsis <k.karkaletsis@gnomon.com.gr>, 
[yes] Licinio Mano <licinio.mano@iuz.pt>,
Marcello Melgara <Marcello.Melgara@cnt.lispa.it>,
[yes] Marcelo Fonseca <marcelo.fonseca@iuz.pt>, 

...

Mindaugas Ajauskas <mindaugas.ajauskas@lispa.it>, 
[yes] Norbert Repas <norbert.repas@elga.gv.at>,
Patrick Ruch <Patrick.Ruch@unige.ch>,
[yes] Per Loubjerg <consult@loubjerg.dk>,

...

[yes] Stéphane Spahni <stephane.spahni@hcuge.ch>,

 

MEETING NOTES

1. OpenNCP Support

2. OpenNCP 2.0.1 Progress

  • Goal 1: PAC + HCER > Audit Trail Messages (Compliance)
      LKM: Check the SPECS and make them available for the dev team.
    • Requested Soren Bittins > sent email epSOS: Audit Trail Specifications > 15 July, 2013 10:30:33 AM GMT+01:00
    • Kostas: modify the audit library
      • It is possible to prepare some development, while waiting for the SPECS;
    • MF + IVO: Could change the component in order to invoke the library;
      • Where to invoke the Audit Trail Messages:
    • Reference Documentation
       D 3.4.2 Common Components Specifications - Version 1 (for XCA or 2.2 for XCF)
    • PAC: currently using identification service and the patient service audit schemas; should be updated when SPECS are in place;
    • HCER: currently using eD service and consent service audit schemas; should be updated when SPECS are in place;
  • Some changes may be needed in order to guaranty compliance with the new SPECS.
    • Reinforce the NEED for the SPECS;
  • Is the compliance with epSOS 1 assurance guaranteed in OpenNCP 2.0.1?
    • Countries moving from OpenNCP 1.1.3 to 2.0.1 should go under a PPT slot before going Operation;
    • 4th PPT: 2º Quarter of September; >
    • 5th PPT: When??
  • Reinforce SPECS need before releasing;
    • Even without the SPECS the release MUST came out;

  • Goal 2: epSOS 1 & 2 > Document
    Jira Legacy
    serverJIRA (openncp.atlassian.net)
    keyPT-295

 

NEXT Steps


  • [LKM - Done] Licinio Schedule 'next' meeting - proposed date July 23rd 30rd, 2013, 10h00 9h00 CET