OpenNCP Weekly Sprint Meeting

4th Jun 10:00 to 11:00  CET

Work RoadMap - epSOS 2 Services

1º Sprint: 28Jan > 8 Fev (2 weeks) > Completed
2º Sprint: 11Fev > 22Fev (2 weeks) > Completed
3º Sprint: 25Fev > 8Mar (2 weeks) > Completed
4º Sprint: 11Mar > 22Mar (2 weeks) (<- both weeks, or perhaps just the last week could be the code freeze?) Completed

...

  • Support OpenNCP 1.1.3 (used in 4th PPT-slot as May 27th - June 7th)
     
  • Release OpenNCP 2.0.0 > 19 June (Thursday) 

 

Agenda

1. PAC QA Stage

2. HCER QA Stage

...

4. 4PPT OpenNCP usage feedback

 

Location

Skype (Gareth > konaboy32 ) + EtherPad (http://meetingwords.com/OuTa9jb29i)

Participants:

Aarne Roosi <Aarne.Roosi@affecto.com>, 

...

Stéphane Spahni <stephane.spahni@hcuge.ch>,

 

 

 

MEETING NOTES

1. PAC QA Stage

- [MF] In progress:
-- Accomplishments: 

...

---- KOSTAS assigned: GPB-12, GPB-13, GPB-14 (Marcelo Fonseca);

2. HCER QA Stage

- Demo???
-- [KH] No demo in place, at this moment.
--- [MF] Will start the functional QA!!!

3. OpenNCP version merging progress (1.1.3 to 2.0.0)

- 27May: 1.1.3 has been merged to the development branch;

...

---- 2.0.0 will only be release only when PAC and HCER services are stable;

4. Move epSOS-Web to a different TaskBoad;

- only 3  countries are using, so it may go for a specific board in order to keep focus on issues that affect most of the PN.
-- ? Should the Gnomon Portal has a separate board?

5. OpenNCP - performance tests

- Konstantin: some limitations found, regarding the performance, happens with lot of transactions e.g. +100

6. Team members availability:

Gareth+team: low availability > in next 2-3 weeks

...

Alexander > Kostas: check availability > main focus PPT slot; after 4thPPT maybe availability will rise;


 

NEXT Steps

- [To Do - Licinio]  Schedule 'next' meeting - proposed date June 4th, 2013, 10h00 CET

...